Orange and Rockland Construction Update – 12//1

Monday 12/2 – Complete rock removal along W. Crescent Ave (sidewalk) & complete the remaining 25 feet of ductbank installation. 1-Lane of traffic will be closed; traffic will be detoured to Ivers Rd. Expecting to work to take place 7:30 – 4.

Tuesday 12/3 – Complete the riser install on N. Franklin Tpke (~10 feet remaining). Expecting to work 7:30-4. 1-Lane of traffic will be closed; traffic will be detoured to Ivers Rd. The work is planned to take place 7:30 – 4.

Wednesday 12/4 – Restoration, Site cleanup, proofing of ducts, and more demobilization activities. (Traffic setup determined by mid-day Tuesday).

Thursday 12/5 & Friday 12/6 – Work resumes in substation access at the end of Heights rd.

Please note that the schedule is subject to change, and we will continue to work with ORU throughout this process and provide updates where possible.